The Structural FX crew was on hand back filling the foundation and preparing to work on the upper floor. Here's Barney working the mini backhoe.
A large order of joists arrived as well as plywood for the back section of the house. Unfortunately the longer front joists are only going to arrive next Monday, delayed because they are being made out of state. The team plans to install the back section en masse tomorrow. Brian said "we'd be able to dance on our bedroom floor Wednesday".
We're trying now to find free clean fill as we are missing dirt on the project site in a pretty major way. There seem to be quite a few postings on Craigslist for this and we are checking these out.